Was doing a wake through the budget module in Nav 2016 and
discovered that when ever you import budget from an excel template that you
previously exported ,The budget figures will not be updated This is a common
problem with the First Nav 2016 Release ,Which Can be Solve by Oneof the following:-
1. The solution is by downloading the cumulative update 7 or above -
this solution only applies to Microsoft partners
2. The second solution is by
modifying the - import budget from excel (81) Process only Report ,By exporting
the same object from a lower version (2013) and Replacing the one of Nav 2016
Developer can easily do the second one without any additional cost